BESS market — India vs Global
- Adiabatic Technologies Pvt Ltd

- Nov 30, 2025
- 6 min read

Battery energy storage systems (BESS) are no longer “nice-to-have” — they’re central to how grids integrate renewables, manage peaks, firm capacity, and create new revenue streams. Below is a compact but detailed comparison of the global and Indian BESS markets (status, drivers, technology, supply chain, financing, risks), followed by practical recommendations for startups like Adiabatic Technologies Pvt. Ltd.
1) Quick snapshot (largest, most important facts)
Global BESS market is large and growing rapidly — estimates put market value roughly ~USD 50–77 billion in the mid-2020s with forecasts that it will roughly double by 2030 (high single- to mid-teens CAGR in most reports). (MarketsandMarkets)
India has surged from almost zero utility-scale deployments a few years ago to a multi-GWh pipeline: as of mid-2025, India had ~13–14 GWh of standalone battery storage under development and several large utility projects announced. Domestic market estimates show sharp growth (CAGR >30% in many forecasts). (Mercomindia.com)
(Global is huge and diversified; India is an accelerating, policy-driven growth market with big utility, hybrid, and merchant experiments.)
2) Market drivers — global vs India (what’s pushing demand)
Global
Rapid renewable (solar/wind) deployment, grid modernization, and markets for frequency response, ramping and capacity. Large mature markets (US, Europe, China, Australia) combine merchant opportunities and utility procurement. Cost declines in cells + system integration + software = more use cases enabled. (MarketsandMarkets)
India
A policy push (national frameworks, VGF and procurement guidelines), ambitious renewable targets, and state/central tenders for hybrid solar+BESS and standalone BESS. India’s drivers include: 24×7 renewable targets, transmission constraints (which favor behind-the-meter and distributed BESS), and peak-management needs in fast-growing demand pockets. The Ministry of Power / MNRE frameworks and VGF push have been explicit catalysts. (Ministry of New and Renewable Energy)
3) Policy & procurement: India’s distinct features
Active central support: National frameworks and operational guidelines (e.g., Viability Gap Funding for BESS; Energy Storage Obligation trajectories) explicitly lower project risk and spur auction volumes. These policies directly enabled state auctions and large developer announcements. (Ministry of New and Renewable Energy)
Auction model + aggressive bidding: India is using competitive tenders aggressively to secure BESS capacity (both standalone and hybrid). That’s accelerating capacity additions but has created concerns about underbidding and thin margins in some tenders. (ieefa.org)
Implication: policy reduces entry friction but raises the technical/contractual bar (penalties, performance requirements, grid interconnection standards).
4) Scale & notable projects (who’s building what)
India’s pipeline includes many large projects (several hundreds to thousands of MWh). Developers and large conglomerates (NTPC, Adani, JSW, ReNew, Avaada) have announced multi-hundred-to-multi-thousand MWh projects and hybrid solar+BESS parks. Examples include very large clustered projects and integrated solar+BESS parks being planned or tendered. (Blackridge Research)
Globally, utility-scale BESS projects are larger and more numerous (US and Australia lead by deployment), and global vendors and integrators are active across regions. (MarketsandMarkets)
5) Technology & cost trends
Cell technology: Li-ion (NMC, NCA, LFP) dominates. Cost declines across cathode active materials, manufacturing scale, and pack-level engineering continue to reduce $/kWh for BESS. Global price trends have supported more 4-hour and longer-duration tenders. (Technavio)
India specifics: LFP is increasingly popular in Indian utility and microgrid installations because of safety and cycle life advantages; however, high-energy-density chemistries are also used where space or weight matter. System integrators emphasize thermal management, local EPC experience, and O&M capabilities. (The Times of India)
6) Supply chain & manufacturing — global vs India
Global: large cell manufacturing scale in China, Korea, and increasingly Europe & US (gigafactories). Pack/system-level integration and inverter + EMS software are diverse and competitive. (MarketsandMarkets)
India: limited cell manufacturing today (though announcements exist); most projects import cells or modules and assemble packs/containers domestically. This creates supply concentration risk (lead times, pricing volatility) — a key pain point for Indian pack makers and integrators. Policies are encouraging local value-add but large-scale domestic cell capacity is still in the ramp-up phase. (Mercomindia.com)
7) Financing and business models
Global: merchant revenues (capacity markets, ancillary services), utility PPAs, and behind-the-meter commercial models are mature in parts of US / Europe. Project financing is increasingly available for well-structured tenders. (MarketsandMarkets)
India: financing is improving (banks, developer balance sheets, specialised funds), but concerns remain about off-take certainty, aggressive auction pricing, and the need for tailored insurance and performance guarantees. Viability-gap funding (VGF) and government-backed tenders reduce some financial risk. (Ministry of New and Renewable Energy)
8) Risks & challenges (where India differs from the global)
Underbidding / thin margins in auctions: Aggressive tenders produce low tariffs but raise execution and credit risk for developers and integrators. (ieefa.org)
Supply chain concentration: import dependence on cells/modules → lead times and pricing volatility. (Mercomindia.com)
Project execution & grid integration: interconnection constraints, variable resource forecasting, and local EPC/O&M capability bottlenecks. (Blackridge Research)
Policy & contract complexity: performance metrics, degradation clauses, battery warranties and end-of-life obligations differ across tenders and must be managed tightly. (Ministry of New and Renewable Energy)
9) Opportunities (high ROI plays for startups & integrators)
Pack engineering for local conditions: thermal, dust, humidity optimization, and safety features tuned to Indian sites. (Higher reliability wins tenders.) (The Times of India)
Fast, reliable supply aggregation: become the predictable cell/pack aggregator for developers — mitigate the “inconsistent & slow-moving cell supply” pain. (Mercomindia.com)
Software & asset optimisation: EMS, predictive maintenance, degradation-aware dispatch to squeeze more revenue and extend life. Global markets show software adds disproportionate value. (MarketsandMarkets)
Hybrid project expertise: design+integrate solar+BESS with firming services and grid code compliance. (Blackridge Research)
Project financing & risk products: guarantee and insurance products for underbidding risks, and performance contracting. (ieefa.org)
10) What this means for an India-first battery startup (for startups like Adiabatic Technologies Pvt Ltd and many more)
Prioritize supply-chain predictability: lock medium-term supply contracts (or strategic cell partners) and consider inventory financing to avoid project delays — this directly addresses your biggest pain point. (Many Indian developers are pursuing similar steps.)
Specialize in product-market fit for Indian tenders: develop BESS SKUs optimized for 4-hour utility-scale and for LFP chemistries (safety, thermal design, modularity). Focus on O&M economics and proven degradation curves.
Offer integrated EMS + degradation-aware warranties: combine hardware with software to increase lifecycle value (sell higher uptime and predictable throughput). Software differentiators attract premium margins.
Select tenders carefully: avoid margin-destructive auctions unless you have a clear supply & financing advantage. Run probabilistic build-cost models that include cell-price volatility and warranty liabilities. (IEEFA and industry reports flag aggressive bidding as a systemic risk.)
Partner for scale: explore JV or long-term supply deals with larger developers (NTPC/Adani/ReNew) for anchor projects; these reduce revenue volatility and open repeat business.
Invest in test-data & certification: proof of cycle-life under Indian climatic conditions will win tenders and reduce perceived risk for financiers.
11) Outlook (next 3–5 years)
Global: continued strong growth; more diversified supply-chain (regional gigafactories), more non-lithium chemistries for niche use-cases, and growing merchant markets where storage stacks multiple revenue streams. (MarketsandMarkets)
India: rapid capacity build (multi-GWh pipeline becoming installed capacity), continued policy support, more hybrid projects, and a maturation of local value-addition. Expect consolidation (larger developers & integrators) and winners who solve supply predictability and O&M. (Mercomindia.com)
12) TL;DR — The one-line takeaway
Globally BESS is a mature, big, and fast-growing market driven by renewable integration and grid services.
In India the market is exploding from a small base, driven by explicit policy and large tenders — but execution depends on supply-chain reliability, prudent tender selection, and strong system engineering. Fix the cell-supply and lifecycle-cost problems, and you secure a long runway. (MarketsandMarkets)
Sources (selected)
MarketsandMarkets — global BESS market forecasts and drivers. (MarketsandMarkets)
Mercom India — India BESS pipeline and development figures (mid-2025). (Mercomindia.com)
MNRE / Ministry of Power — Operational guidelines, VGF scheme, and National Framework for energy storage. (Ministry of New and Renewable Energy)
IEEFA analysis on aggressive bidding and execution risks in India. (ieefa.org)
Industry project lists & major developer announcements (Blackridge Research, Adani, Avaada, etc.). (Blackridge Research)